Choosing a contractor is not something you do on price alone. Two quotations with different amounts often do not describe the same work. One includes the finishing, the other puts it in a provisional sum. So first compare exactly what is being delivered, and only then the price. Also look at the schedule, the arrangements for extra work, the payment terms and who your point of contact is during the build. With a few targeted questions you quickly see which contractor suits your plan and budget.
Make sure every contractor prices the same plan. Pass on the same drawings, the same wishes and the same finish. Ask for a quotation with a clear description per item, so you can put the items side by side.
Then list the differences. If something is included by one and not by the other, ask why. A low price that consists mainly of omitted items still becomes expensive during the build.
A provisional sum is a provisional amount for something that has not been chosen yet. Provisional sums that are too low make a quotation look more attractive than it is. In building materials are getting more expensive we explain how provisional sums work and how to deal with them.
Extra work is work that is added during the build. Agree in advance how it will be priced and that it will only be carried out after your approval. That way you keep a grip on the budget.
Ask who carries out the work and who your point of contact is. At Bouwbedrijf R. Vlieland the same project manager oversees all the work, from discussing your wishes to completion. That continuity prevents information from getting lost along the way.
Also ask about previous work similar to your plan, and read reviews. On our projects page you can see what we have built. You can read more about how we work on our about us page.
Compare the price with rough market ranges, such as in what does a renovation cost. If one quotation is much lower than the rest, look extra carefully at what is missing. If it is higher, ask what extra is included.
Also pay attention to VAT. For renovation, 21% generally applies to labour and materials, with a reduced rate on labour for insulation work in homes older than two years. See renovation and VAT.
A good agreement describes the work, the price, the provisional sums, the schedule, the payment instalments and the arrangements for extra work. Pay in instalments that match progress, and never the larger part up front.
Also check the validity of the quotation and whether it contains a price escalation clause. If you are unsure about any point, ask before you sign. A contractor who explains things calmly is usually easy to reach during the build as well.
Arrange a site visit for every quotation. A contractor who has seen your house prices more accurately and often spots points straight away that the drawings do not show.
Two to three quotations is often enough to get a good picture. More quotations make comparing harder and cost you a lot of time. It is better to deliberately choose a few contractors who suit the type of work.
Not necessarily. First check whether the quotations describe the same work. A lower price can mean that items are missing or that provisional sums have been estimated low.
Usually in instalments linked to the progress of the work, with a final instalment on completion. Agree this clearly in advance in the contract. Never pay a large part up front without work to show for it.
On our request a quotation page you describe your plan, with photos or drawings if you have them. We then contact you for a conversation and a visit. After that you receive a tailored quotation.
Call or message us with your question. We are happy to visit and look at your situation, free of charge.
Request a quote Get in touchCall or message Richard Vlieland on +31 6 11 78 63 20, or request a free quote. We are happy to come and have a look.
Request a quote More information